Cold numbers
49 issues made it safetly in, only 2 issues this week didn't quite make it. Nothing was delayed. Thats a very impressive 96% rate.

Notes:

  • Christmas is nearly here, as we all enjoy the celebrations as much as you HQ will be closed from Wednesday 25th through Wednesday 1st.
  • As you're planning your new features for Moodle 2.7 don't forget to think about phpunit and behat tests to accompany them, it'd make us extra happy.

Interesting happenings from this weeks run:

  • MDL-42625 Hardcoded behat waits have been removed, tests should be feeling faster.
  • MDL-40058 The add_to_log conversion continues on, wiki was completed this week.
  • MDL-42932 Calendar types can now be set at a site level.
  • MDL-35024 Numerous functions deprecated in 2.0 were removed.
  • Several JS blocks we converted to modules built by shifter.

Warm thanks:

This week goes to Jason Fowler who peer-reviewed 11 of the 49 issues that were made it through integration this week. Big thanks Jason helping to keep the development ball rolling.

Regards Sam