Course Completion Date 1970

Course Completion Date 1970

by Theodora Kakouri -
Number of replies: 3

Hi, everyone!

Moodle 3.9.1+ (Build: 20200717)

I am running an issue with dates shown on course completion report.

I had to change the enrollemnt date on a current course in order to extend it.

After thw above, the course completion report shows Jan 1 1970 instead of March 11, 2021 which is the date edited for the current course.

In addition enrolled users cannot access assignement and additionally, teachers are not able to GRADE assignments.

Please advise!

Thanks

Theodora

Attachment Dates-Error.png
Average of ratings: -
In reply to Theodora Kakouri

Re: Course Completion Date 1970

by Randy Thornton -
Picture of Documentation writers
Theodora,

A date of Jan-1-1970 means the date setting is empty or set to 0.

The date above is the one set in Course admin > Course completion :: Condition Date, not in any of the enrolment methods. Is the date set in Course completion set correctly?

Randy
Average of ratings: Useful (1)
In reply to Randy Thornton

Re: Course Completion Date 1970

by Theodora Kakouri -
Randy,
Thanks for replying! The Completion Date is set correctly (see attachment) as well as the Course End date! 

Attachment Completiondate.png