Activity Completion Report Wrong Date Recorded

Activity Completion Report Wrong Date Recorded

by Lisl Cammile Glivano -
Number of replies: 1

I'm getting this date when downloading the Activity Completion from reports, however, in gradebook, it shows the correct date.

What could've caused this issue?



Thanks, 

Lisl

Average of ratings: -
In reply to Lisl Cammile Glivano

Re: Activity Completion Report Wrong Date Recorded

by Randy Thornton -
Picture of Documentation writers
Lisl,

This is because the activity is not yet complete. It puts the proper date when the activity is completed.

Until then, it uses the placeholder of 0 which refers to the start of the Unix Epoch time https://en.wikipedia.org/wiki/Unix_time which is UTC January 1, 1970, 00:00 hours. Moodle stores dates internally as the number of seconds since this time.

(You see 10:00 AM on your report due to your timezone offset from UTC/GMT; some users or sties may see dates of December 31, 1969 due to the offset.)

If the gradebook date is accurate, that indicates the user got a grade at that time, but that the activity is still not completed. There may be other criteria for completion such as the grade may not be a passing grade, etc. depending on how you have set up the activity completion for that activity.


Randy