HI Gordon, others,
Not sure what I am doing incorrectly. I have put two very simple HotPots chained together in Gordons 2.4 server: http://bateson.kanazawa-gu.ac.jp/24/course/view.php?id=2 (Trial - Jeff Finnan)
I set the conditions so that one needs 90% to advance or same task and the second quiz requires the first quiz to be completed first as a preconditon as I would do with a QuizPort. I have the chain set as force resume.
I set my role as student.
When I finish the first quiz and back out and go back in it says start a new chain attempt and starts me at the first quiz.
Where am I messing this up?
Thanks,
Jeff