Hi
I would like to ask, if there is some block or any other way how to set start and due dates for example to multiple assignments (or any other activities with this dates)?
I know i created some tweaks for older version to set all due dates for assignments, quizzes etc. in course. I don't remember why i haven't implemented this to new version. I think i found some 3rd party block which looked like it does what i want, but now i just don't remember
Any ideas welcomed.
PK
Hi
I didn't remember, so i made small block.
Teacher can modify start/end dates for various Activities, for more instances of this activity. Set same start/end date for all instances, delay start/end for X days.
I betatested this block for a while, so its looking good, but i will appreciate another tester. Please, test it on your test server at first. It is not meant to production servers yet.
PK
I didn't remember, so i made small block.
Teacher can modify start/end dates for various Activities, for more instances of this activity. Set same start/end date for all instances, delay start/end for X days.
I betatested this block for a while, so its looking good, but i will appreciate another tester. Please, test it on your test server at first. It is not meant to production servers yet.
PK
sorry i did not read your first post.
You can do it with the planning block and does it graphically, is a gantt diagram
you can graphically change the dates (not hours/minutes)
you can find it here
http://moodle.org/mod/data/view.php?d=13&rid=497
You can do it with the planning block and does it graphically, is a gantt diagram
you can graphically change the dates (not hours/minutes)
you can find it here
http://moodle.org/mod/data/view.php?d=13&rid=497
There is Course Date Manager block. It is very powerful, but does not work very well with newer versions of moodle.